Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation

Business

Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation

F. Acebes, J. M. González-varona, et al.

Discover a groundbreaking approach to project risk prioritization developed by F. Acebes, J. M. González-Varona, A. López-Paredes, and J. Pajares. This innovative research utilizes Monte Carlo Simulation to provide a quantitative assessment of risks, enabling project managers to effectively allocate resources and focus on critical risks impacting duration and cost.

00:00
00:00
~3 min • Beginner • English
Abstract
The project managers who deal with risk management are often faced with the difficult task of determining the relative importance of the various sources of risk that affect the project. This prioritisation is crucial to direct management efforts to ensure higher project profitability. Risk matrices are widely recognised tools by academics and practitioners in various sectors to assess and rank risks according to their likelihood of occurrence and impact on project objectives. However, the existing literature highlights several limitations to use the risk matrix. In response to the weaknesses of its use, this paper proposes a novel approach for prioritising project risks. Monte Carlo Simulation (MCS) is used to perform a quantitative prioritisation of risks with the simulation software MCSimulRisk. Together with the definition of project activities, the simulation includes the identified risks by modelling their probability and impact on cost and duration. With this novel methodology, a quantitative assessment of the impact of each risk is provided, as measured by the effect that it would have on project duration and its total cost. This allows the differentiation of critical risks according to their impact on project duration, which may differ if cost is taken as a priority objective. This proposal is interesting for project managers because they will, on the one hand, know the absolute impact of each risk on their project duration and cost objectives and, on the other hand, be able to discriminate the impacts of each risk independently on the duration objective and the cost objective.
Publisher
HUMANITIES AND SOCIAL SCIENCES COMMUNICATIONS
Published On
May 24, 2024
Authors
F. Acebes, J. M. González-Varona, A. López-Paredes, J. Pajares
Tags
risk prioritization
Monte Carlo Simulation
resource allocation
cost impact
project duration
risk assessment
MCSimulRisk
Listen, Learn & Level Up
Over 10,000 hours of research content in 25+ fields, available in 12+ languages.
No more digging through PDFs, just hit play and absorb the world's latest research in your language, on your time.
listen to research audio papers with researchbunny